Repair of oil pipeline in Gulf of Thailand expected to take ten days

Repair of oil pipeline in Gulf of Thailand expected to take ten days

13 Sept 11:10 Key points summarised by AI
  • The 10-day repair of the ruptured submarine oil pipeline will begin after a two-day process to remove 12,000 litres of residual crude oil.
  • The repair involves injecting sealant into the pipe's cracks, wrapping defects with special adhesive, and conducting tests to ensure complete sealing.
  • Star Petroleum Refining (SPRC) will operate under close supervision from experts and agencies like the PCD, with divers monitoring for leaks and ten vessels equipped with booms and dispersants on standby to contain any potential spills.
  • A team will be deployed to fully record the repair work, as the pipeline is considered a crucial piece of evidence that must be protected.