BMA drops Khubon-Bang Chan project after costs soar
The Bangkok Metropolitan Administration (BMA) canceled the Khubon-Bang Chan water retention project due to its cost soaring to an estimated 11 billion baht, making it economically unviable.
Project costs escalated significantly due to increased land prices and additional expenses for constructing water barriers, floodgates, pumping stations, and channels.
Experts revealed the planned 870,000 cubic meter retention area would only effectively manage 500,000 cubic meters, rendering it insufficient for Bangkok's flood challenges.
The decision sparked criticism over the project's decade-long delay since its 2011 proposal, which allowed costs to inflate while Bangkok continued to face severe flooding.
Officials concluded that even if completed, the project's limited capacity would not have absorbed recent heavy rainfall, emphasizing the need for larger-scale water management solutions.
AI In-briefToday 13:32
SRT sets deadline to end dispute with CP Group over high-speed airport links
The State Railway of Thailand (SRT) has set November 28 as the deadline to resolve a six-year dispute with Asia Era One (a CP Group subsidiary) concerning the high-speed rail project linking three major airports.
Asia Era One has refused to proceed with the project, insisting on terminating the concession contract, prompting SRT to issue a Notice To Proceed and threaten legal action if the conflict remains unresolved by the deadline.